Well for the house we have our plumbing all roughed in for the basement. That was done all last week.
Today they came and poured half of our basement floor. We also have our temporary heat on now too. I think by the end of the week or the beginning of next week we will start seeing some siding and windows and doors going in!! That will be wonderful to get that all done so they can start working on the inside.
That is about all that has happened will update with some picture maybe on Wednesday!!